Work Order | Contractor | Work Description | Unit | Quantity | Manpower | Materials | Machinery | Deadline | Status |
---|---|---|---|---|---|---|---|---|---|
CWO-2024-0825 | EarthMovers Ltd | Site Excavation & Leveling | Cubic Meter | 1,500 |
6 Laborers
2 Supervisors
|
Diesel Fuel
Safety Barriers
|
2 Excavators
1 Bulldozer
|
25 Aug 2024 | In Progress |
CWO-2024-0826 | Concrete Masters | Foundation Concrete Pouring | Cubic Meter | 300 |
8 Masons
10 Helpers
1 Engineer
|
M35 Concrete
Shuttering Ply
|
Concrete Pump
Vibrators
|
28 Aug 2024 | Scheduled |
CWO-2024-0827 | SteelErect Co. | Structural Steel Erection | Ton | 50 |
4 Welders
6 Riggers
1 Safety Officer
|
Steel Beams
Bolts & Nuts
|
2 Cranes
Welding Machines
|
01 Sep 2024 | Completed |
CWO-2024-0828 | PowerLine Electrics | Electrical Conduit Installation | Meter | 2,500 |
5 Electricians
3 Helpers
|
PVC Conduits
Junction Boxes
|
Core Cutting Machine
|
05 Sep 2024 | Delayed |