Site Work Orders

Daily Construction Activities

Work Order Contractor Work Description Unit Quantity Manpower Materials Machinery Deadline Status
CWO-2024-0825 EarthMovers Ltd Site Excavation & Leveling Cubic Meter 1,500
6 Laborers
2 Supervisors
Diesel Fuel
Safety Barriers
2 Excavators
1 Bulldozer
25 Aug 2024 In Progress
CWO-2024-0826 Concrete Masters Foundation Concrete Pouring Cubic Meter 300
8 Masons
10 Helpers
1 Engineer
M35 Concrete
Shuttering Ply
Concrete Pump
Vibrators
28 Aug 2024 Scheduled
CWO-2024-0827 SteelErect Co. Structural Steel Erection Ton 50
4 Welders
6 Riggers
1 Safety Officer
Steel Beams
Bolts & Nuts
2 Cranes
Welding Machines
01 Sep 2024 Completed
CWO-2024-0828 PowerLine Electrics Electrical Conduit Installation Meter 2,500
5 Electricians
3 Helpers
PVC Conduits
Junction Boxes
Core Cutting Machine
05 Sep 2024 Delayed